11.01.2021, 22:40
After testing via Wireshark i am not that sure.
When using CFC from Siemens i get "Process fault" and "Unreliable other". When testing via Yabe at the same time, no connection is possible to the LM5.
After a little while it might go back working again. Before it all happens again.
Everything looks ok at the LM5 at the same time, and no problem entering it. Attached also system load, i guess this shows that the bacnet process is running.
When using CFC from Siemens i get "Process fault" and "Unreliable other". When testing via Yabe at the same time, no connection is possible to the LM5.
After a little while it might go back working again. Before it all happens again.
Everything looks ok at the LM5 at the same time, and no problem entering it. Attached also system load, i guess this shows that the bacnet process is running.